We're officially on to Phase 2 of Liberty's Southern District Supply Constraint Mitigation Project.
Phase 1 included the construction of the Harvey Road Gate Station in Londonderry. Now, Phase 2 focuses on installing approximately two miles of natural gas pipeline to connect the gate station to our existing distribution system in Manchester. Once complete, this important infrastructure project will strengthen reliability and support future growth in the greater Manchester and Nashua areas.
Follow along with project updates below!
November 2026
Construction is moving right along!
Since August, crews have installed more than 6,120 feet of natural gas pipeline, putting us past the halfway point of the approximately 9,400-foot project.
The new pipeline will connect the Harvey Road Gate Station to our existing natural gas distribution system, strengthening reliability and supporting future growth in the greater Manchester and Nashua areas.
Next steps include continuing pipeline installation and installing a new regulator vault near Brown Avenue, remaining on track for completion by the end of 2026.


And the timing couldn't be better! The Harvey Road Gate Station will be commissioned and placed into service just in time for some of New England's coldest winter months. With January and February typically bringing some of the highest demand for natural gas, the new infrastructure will strengthen our system's ability to reliably serve customers when they need it most.